A new project manager assumes a project after a phase closing. The new project manager suspects that there were delays during the previous phase. What should the project manager review to confirm this?
A. Lessons learned
B. Project charter
C. Schedule performance index (SPI)
D. work performance reports
一名新项目经理在项目的某个阶段收尾后接管该项目。新项目经理怀疑前一个阶段中存在延期。若要确认这一点,项目经理应审查下列哪一项?
A.经验教训
B.项目章程
C.进度绩效指数(SPI)
D.工作绩效报告
A new project manager assumes a project after a phase closing. The new project manager suspects that there were delays during the previous phase. What should the project manager review to confirm this?
A. Lessons learned
B. Project charter
C. Schedule performance index (SPI)
D. work performance reports
一名新项目经理在项目的某个阶段收尾后接管该项目。新项目经理怀疑前一个阶段中存在延期。若要确认这一点,项目经理应审查下列哪一项?
A.经验教训
B.项目章程
C.进度绩效指数(SPI)
D.工作绩效报告